Smooth running part in the construction of the sewerage system in the municipality of Komenda

31 August 2016
Smooth running part in the construction of the sewerage system in the municipality of Komenda

In the Municipality of Komenda is working on a project for drainage and wastewater treatment in the area of ​​Domžale-Kamnik, sewage Waterfront in the municipality of Komenda, carried out according to schedule. Work is carried out mainly through the neighborhoods of residential houses. Before the final asphalting of roads will be provided for the arrangement of borders and proper drainage. Municipality of Komenda simultaneously with the construction of the sewage system at its own expense on certain sections also renews worn salonite water pipes.

In the village Suhadole the laying of sewer pipes is completed, governing is still needed for the drainage of seepage water streets and limit the hearing, which took place in late August and early September. Asphalt Suhadol provided in the middle of September.

Works in Žejah were completed with works on the production site, is being implemented to a connecting sewer line between the houses.

In the village Bridge road works for the nursery Gašperlin that passes NT Logistics, the majority concluded. Laid asphalt and landscaped sidewalk with curbs, which were at that part where it had not previously been financed by the citizens themselves.

Moste work currently underway between the residential houses, where it will be on a specific part rehabilitate the water supply.

In early September, the labor migrating to the area of ​​the racetrack. They will start with the parts of the playground, which will be built pumping station, then will the sewage pipe navigate between Prince's stream and the mountain racetrack near Komenda. Given that this is the way past the school, it will be for the safety of school children are taken care of by the guardrails. At a time when the construction will move to the narrow path between the hippodrome and the Prince's stream, it will only be fully closed and the pupils temporarily regulate the business building racecourse.

During the show, in the municipality of Komenda, this is the 7th, 8th and 9th October will work on the site stopped. It will be ensured a smooth unwinding of the fairgrounds.